Resolved: Willard Hub Site Electrical Upgrade

ENCS will be replacing the Uninterruptible Power Supply (UPS) system that serves the Willard HUB site on Tuesday April 11th, 2017, starting at 5AM with work expected to be completed by 5PM.

In order to perform this work, all equipment at the Willard HUB site will only be supplied by NORMAL building power. This power source will not have the benefit of backup protection from a generator or a UPS. We anticipate the transfer and operation of the equipment on the NORMAL power source to NOT be service affecting and users will not see any outage.

In the event of an unplanned power event on campus to the Willard electrical feed, ECNS services would go offline for the duration of the electrical outage or until we would be able to complete the upgrade and transfer back to UPS / Emergency Power.

Services that have the potential to be affected include:
-Willard Layer 2 and 3 Network connections that are not redundant.

– VoIP, Wireless, and Backbone services in the following buildings are subject to this alert:

Schwab
Reber
300 BLDG
Sparks
Hosler
EngUnit A&B
EE West
EE East
Calder Square
Steidle
James BLDG
ARL
Deike
Rider House
Sackett
Rider
Walker
Allenway
Marion Place
224 South Allen
Hammond
Elliott
Downtown Theatre
The Towers
Willard
141 West Beaver
Power Plant
Carnegie
Old botany
Bag House
Hintz

Again, we anticipate NO service outages related to this work, only if there is an unplanned and external electrical outage while this work takes place since the equipment will not have backup power.

Please reference SNow Change – CHG0040552

More information: Resolved: Willard Hub Site Electrical Upgrade

Story added 12. April 2017, content source with full text you can find at link above.